Client:
InditexPAK ARAB Refinery Limited (PARCO)
From January 2026 to July 2027, PITCO has been providing Project Management Consultancy (PMC) and Owner’s Engineer services to PAK ARAB Refinery Limited (PARCO) for the development of Phase-I of Project Shams, comprising solar PV systems at five strategically located PARCO stations and terminals across Pakistan. The project covers a combined solar capacity of approximately 6.33 MW at Shikarpur (3 MW), Korangi (2.6 MW), Faisalabad (0.3 MW), Machike (0.3 MW) and Keamari (0.13 MW rooftop). PITCO is supporting PARCO as part of the Integrated Project Management Team (IPMT), providing comprehensive technical, commercial, contractual and project management support throughout the EPC project lifecycle.
The services include feasibility revalidation, EPC tender documentation, bidding strategy, technical bid evaluation, financial model updates, design and engineering review, procurement and construction monitoring, QA/QC and HSE compliance, contract and change management, claims review, schedule and cost control, inspection, testing and commissioning, and project handover. PITCO has also been supporting PARCO in safety studies, design reviews, engineering query resolution, interface coordination, EPC progress monitoring, invoice verification and payment certification, procurement and logistics monitoring, equipment inspection, pre-commissioning and commissioning activities, performance testing, punch-list management and verification of contractual performance guarantees. The assignment further includes support for provisional acceptance, independent gate reviews, completion documentation, O&M requirements and, where required, selection of the O&M contractor.